# Planning – Trailer and container availability status on the resource board

The resource board now reflects **real-time availability** for trailers and containers. As soon as a load is marked as completed, the linked trailer or container immediately shows as **Available**. There is no need to wait until the end of the day.

## How availability status works {#h_a45831c510}

Trailers and containers on the planning resource board show one of the following statuses:

| **Status** | **Meaning** |
| --- | --- |
| **Available** | The resource is free and can be assigned to a new load |
| **In use** | The resource is assigned to an active (not yet completed) load |
| **Parked** | The resource is parked and not currently in active use |

## Status update on load completion {#h_80b6a94776}

Previously, a trailer or container stayed marked as **In use** or **Parked** for the rest of the day, even after its load was completed. This made it unclear whether a resource was actually free for reassignment.\
Now, the availability status updates **immediately** when a load is completed:

-   As soon as a load is **marked as completed** (via the driver mobile app or manually by a planner), the linked trailer or container switches to **Available** on the resource board
-   Planners can reassign the resource to a new load right away

![](https://help.qargo.com/media/3a4eae9f1264-image.png)

* * *

## How to mark a load as completed {#h_c8c51f8c06}

A load can be completed in two ways:

1.  **Driver mobile app**: The driver marks all stops as delivered in the Qargo mobile app
2.  **Manually by a planner**: Open the load in Qargo and update the load status to **Completed**

Once either action is taken, the trailer or container linked to that load immediately appears as **Available** on the resource board.

## Limitations {#h_63c384041e}

-   The status update depends on the load being **properly marked as completed** in Qargo. Loads that are not yet completed continue to show the resource as **In use**, even if the load has physically ended.
-   **Manual yard movements** made outside of Qargo (e.g., moving a trailer without creating or completing a load in the system) are not tracked and do not update the availability status.
-   This applies to both the **trailer planning** and **container planning** views.


## Related articles

- [Resource availability overviews](https://help.qargo.com/us/articles/269363-resource-availability-overviews.md)
- [Planning - Container planning](https://help.qargo.com/us/articles/133853-planning-container-planning.md)
- [Planning — Per-day resource availability in To Plan: Resources](https://help.qargo.com/us/articles/712533-planning-per-day-resource-availability-in-to-plan-resources.md)
- [Planning: plan resource to order](https://help.qargo.com/us/articles/292119-planning-plan-resource-to-order.md)
- [Trailer planning](https://help.qargo.com/us/articles/133852-trailer-planning.md)